Our Project
Six laning from Kodungallur to Edapally section of NH-66 (old NH-17) from Design Ch.397+750 (Ex. Km 411.850) to Design Chainage 423+780 (Ex. Km 343.330 of NH-47) in the State of Kerala on Hybrid Annuity Mode under BharatmalaPariyojana.
Date of Signing of Concession Agreement: 14.03.2022
| Bid Project Cost | 1617.20 Cr. |
| Appointed Date | 25.10.2022 |
| Construction Period | 910 Days |
| Scheduled Date of Completion | |
| Actual Date of Completion | 21.04.2025 |
| O&M Period (Years) | 15 Years |
Utility Shifting Status
| Electrical | 98.24% work completed |
| PHE | |
| Removal of Encroachment | Completed |
| Tree Cutting | Completed |
| Water | 77.80% work Completed |
Preconstruction Activity
| Camp & Establishment Set up | Completed |
| Casting Yard including gantries | Completed |
| Batching Plant Set up with all equipment | Completed |
Land Acquisition Status
| Total Land Required | Completed |
| Total Land Available | Yes |
| Additional Land Requirement | NA |
| Likely availability of remaining land | NA |
| Project works Status | As on date 11.02.2026 work completed – 70.44% |
Major Bridge
| Foundation | 100% work Completed (102 Nos) |
| Substructure | 100% work Completed (102 Nos) |
| Superstructure | 92.39% work Completed (Total-90 Nos & Completed-85 Nos) |
Minor Bridge
| Foundation | 100% work Completed (43 Nos) |
| Substructure | 100% work Completed (43 Nos) |
| Superstructure | 100% work Completed (28 Nos) |
ROB
| Foundation | 100% work Completed (26 Nos) |
| Substructure | 100% work Completed (26 Nos) |
| Superstructure | 88% work Completed (Total - 25 Nos & Completed-22 Nos) |
Underpass
| Foundation | 98.28% work completed (Total – 58 Nos & Completed – 57 Nos) |
| Substructure | 98.28% work completed (Total – 58 Nos & Completed – 57 Nos) |
| Superstructure | 97.06% work completed (Total – 34 Nos & Completed – 33 Nos) |
Box Culvert
| Foundation | 47 Nos Completed |
| Substructure | 47 Nos Completed |
| Superstructure | 47 Nos Completed |
| Foot over Bridge | NA |
| SERVICE ROAD | 60.34% work completed (Total – Km 44.996 & Completed – Km 27.15) |
| RCC DRAIN | 85.73% work completed (Total – Km 44.996 & Completed – Km 38.57) |
| MAIN CARRIAGEWAY | |
| Total Physical Progress | As on date Progress – 71.63% (10.03.2026) |